Project Progress

This topic describes the differences between Project Progress in Infor LN FP5 and in Infor LN FP6 that are not already discussed in other differences topics.

New and changed functionality

  • Project Origin
    The Calculate Interim Result defaults (tpppc4205m000) session is added. You can use this session to calculate the percentage completed or earned revenue factor for a range of projects (instead of one-by-one).