Correct display of outdated SFC orders in Resource Order PlanThe Resource Order Plan (cprrp0530m000) session displays the capacity use for planned orders. Infor LN FP5 In Infor LN FP5, in some cases the planned production orders that started before the scenario start date are not correctly included in the resource order plan. New in Infor LN FP6 In Infor LN FP6, if you select a period length other than Detail, the capacity use of production orders that start before the start of the scenario and end after the start of the scenario is added to the first period of the resource order plan. The available capacity in the past is always displayed as 0. If some production orders started before the scenario start date, the free capacity in the period in which the capacity is required can be displayed as negative. In that case, the cumulative free capacity can be displayed as negative in the period that includes the current date.
| |||