Convert Planned and Scheduled Supply to Confirmed Supply (cpvmi1210m000)

Use this session to generate confirmed supply based on planned orders and scheduled receipts. Scheduled receipts include scheduled purchase receipts, scheduled production receipts, and scheduled distribution receipts.

To define confirmed supply

To define the confirmed supply manually, use the Item Customer Plan (cpvmi0520m000) session.

To generate confirmed supply based on planned orders and scheduled receipts, use this session.

After LN generates confirmed supply, you can view and optionally modify the confirmed supply in the Confirmed Supply to Customer (cpvmi0108m000) session, before sending the infomation to the customer.

Note

If the confirmed supply has been approved, you can no longer modify the confirmed supply of the current revision. After you receive the next forecast revision from your customer, you can also create a new version of the confirmed supply.

 

Scenario
The identification of an overall planning solution.

Each scenario represents one overall planning solution, and involves particular settings for the planning of items and resources. You can use scenarios to analyze and compare various planning options and to find the best planning solution. For example, you can vary demand forecasts or sourcing strategies.

One of the scenarios is the actual scenario, which corresponds with the actual planning situation. You can only transfer planned orders and production plans from the actual scenario to the execution level of LN.

From Plan Item
An item with the order system Planned.

The production, distribution, or purchase of these items is planned in Enterprise Planning based on the forecast or the actual demand.

You can plan these items by means of the following:

  • Master-based planning, which is similar to master production scheduling techniques.
  • Order-based planning, which is similar to material-requirements planning techniques.
  • A combination of master-based planning and order-based planning.

Plan items can be one of the following:

  • An actual manufactured or purchased item.
  • A product family.
  • A basic model, that is, a defined product variant of a generic item.

A group of similar plan items or families is called a product family. The items are aggregated to give a more general plan than the one devised for individual items. A code displayed by the item code's cluster segment shows that the plan item is a clustered item that is used for distribution planning.

Planner ID
The planner that is entered for the item in the Planner field of the Items - Planning (cprpd1100m000) session.
Default Warehouse
The warehouse that is entered for the item in the Default Warehouse field of the Items - Planning (cprpd1100m000) session.
Sold-to Business Partner
The sold-to business partner for which you carry out the planning.
Order Status
The order status of the planned orders on which the confirmed supply is based.
Simulation
If this check box is selected, the session does not actually generate confirmed supply, but only prints the requested reports.
Replan Forward
If this check box is selected, and the replenishment method is based on Inventory Level and the actual stock drops below the agreed minimum inventory level, the session generates a planned order for which the Order Release field is set to To be released.
Update Pegging Forecast - Confirmed Supply
If this check box is selected, the session creates and updates soft pegs to link the generated confirmed supply to the forecast that caused the demand.
Generate Only Confirmed Supply Type 'Stock'
If this check box is selected, only generates confirmed supply of confirmed supply type Stock. This setting can be useful if you manually define the confirmed supply, because you cannot manually enter confirmed supply of confirmed supply type Stock.
Print Differences
If this check box is selected, the session reports the differences between the new values and the previous values of the confirmed supply. If no differences are found, no report is printed.
Print Results
If this check box is selected, the session reports the calculated confirmed supply.

 

Continue
Starts generating the confirmed supply.