Select how the item orders will be sorted in the Item Order Plan (cprrp0520m000) session.
Allowed values
- Item
- Item-Project
- Item-Project Peg
Item Order Plan - Selection (cprrp0521s000)Use this session to specify a scenario, a plan item and a period length for which you want to analyse the item order plan. The result is shown in the Item Order Plan (cprrp0520m000) session.
View by View by Select how the item orders will be sorted in the Item Order Plan (cprrp0520m000) session. Allowed values
Scenario Enter the scenario of which you want
to see the item order plan. Plan Item Define the plan item for which you want to see the item order plan. Project Element Activity Period Length The length of the period units that are used for the item order
plan. Allowed values
Show Order Distribution If this check box is selected, the order distribution
lines for the production order are shown in the Item Order Plan. Note
Start Date In this field, you can select the start date for the item order
plan from the displayed calendar. Hide 'Empty' Periods If this check box is selected, the empty periods are
hidden when the results are displayed in the Item Order Plan (cprrp0520m000) session. If, for the plan item, no planned inventory transactions, or simulated values are present in LN, periods are empty. Display Cost Peg Transfers
| |||