Planned Cost Peg Transfers (cprrp0130m000)

Use this session to enable the cost transfer of project peg excess inventory.

 

Scenario
The scenario for which LN displays the exception messages for the specified resource.

.
Transfer
View the orders selected for transfer.
Plan Item
An item with the order system Planned.

The production, distribution, or purchase of these items is planned in Enterprise Planning based on the forecast or the actual demand.

You can plan these items by means of the following:

  • Master-based planning, which is similar to master production scheduling techniques.
  • Order-based planning, which is similar to material-requirements planning techniques.
  • A combination of master-based planning and order-based planning.

Plan items can be one of the following:

  • An actual manufactured or purchased item.
  • A product family.
  • A basic model, that is, a defined product variant of a generic item.

A group of similar plan items or families is called a product family. The items are aggregated to give a more general plan than the one devised for individual items. A code displayed by the item code's cluster segment shows that the plan item is a clustered item that is used for distribution planning.

Quantity
Warehouse
The warehouse from and to which the item is normally delivered.

Allowed values

For a non-clustered item this must be a warehouse in the item's logistical site.

The warehouse of a clustered item must belong to the item's cluster.

Effectivity Unit
A reference number, for example a sales order line or a project deliverable line, that is used to model deviations for a unit effective item.
Requirement Date
Order Status
The status assigned to a planned order in Enterprise Planning.

The order status can either be:

  • Planned
  • Firm Planned
  • Confirmed

Allowed values

Order Status

Planner
The employee or department responsible for planning the production, purchase and distribution of items. The planner takes into account the inventory levels, availability of materials, and capacities of resources, and reacts on signals such as rescheduling messages that LN generates.
From Project
The range of projects from which excess inventory is transferred.
From Element
The range of elements from which excess inventory is transferred.
From Activity
The range of activities from which the excess inventory is transferred.
Excess based on
Select the option excess is based on:

Allowed values

  • Inventory
  • Scheduled Receipts
Hidden Fields
Planning Group
Select the range of planning groups for which orders will be generated.
.
Inventory Valuation

 

Confirm
Start the Confirm (cprrp1200m000) session.
Transfer
Start the Transfer Order Planning (cppat1210m000) session.
Pegging - Upstream
Starts the pegging browser session for components supplied to execute this planned order.
Pegging - Downstream
Starts the pegging browser session for products produced from the main item this planned order.