Offsetting distribution ordersDistribution planning is based on supplying relationships, as specified in the Supplying Relationships (cprpd7130m000) session. Similar to purchase planning, first a supplying source (warehouse cluster) is chosen, after which the distribution order is planned. The lead time of the distribution order can be planned as follows:
Transportation time If a carrier is provided in the supplying relationships, transportation time is planned between the addresses of the supplying warehouse and the receiving warehouse. The logic is the same as for planned purchase orders. Note If no distance is defined for the addresses, the calculated transport time is zero (no warning is given). ![]() Distribution orders with carrier Supply time If no carrier is provided, the supply lead time of the Supplying Relationships (cprpd7130m000) session is used instead. The supply resource is used to link to the calendar. ![]() Distribution orders without carrier
| |||