Production order planning of generic items

The generic routing, defined in the Generic Item - Structure (tipcf3100m100) session, differs from the normal routing. Which operations are used in the routing, depends on the configuration.

Example

Two operations might be exclusive: either operation 10 is selected, or operation 20. As a result, a sequence of operations is not required.

Therefore, the operation of a generic routing has several parameters for planning:

  • Planned Production Time
  • Planning Percentage
  • Lead Time Offset

For the lead time, the planning percentage is taken into account.

Operation lead time = planned production time * planning percentage

The lead time offset is used to determine the start of the operation sequence.

Planned production order for generic item