Show CTP detailsIf you select the Show CTP Details check box in the ATP Handling (cprrp4800m000) session, a graphical browser called Capable to Promise Overview is generated, in addition to the ATP Overview report. The overview provides detailed information below each delivery line with information about the component and capacity constraints encountered during the CTP check. This Capable to Promise overview, therefore, only provides additional information when component or capacity CTP is applied. Otherwise, both reports return the same result. Example of capable to promise
overview: Suppose a quantity of 247 pieces of end item JOSUEF11 is
required. This item has the following multilevel bill of material: ![]() The components JOSUEF14 and JOSUEF17 are the only components in this product structure that are critical in CTP. The other items in the bill of material all have the Component CTP check box selected in the Items - Planning (cprpd1100m000) session. Capacity is excluded from this example. Note The Component check box is selected as the type of check. The Show CTP Details check box is also selected, which indicates that a separate capable to promise overview will be generated in addition to the ATP overview report. The following is shown on the report for the fixed warehouse check : ![]() The capable to promise overview for this fixed warehouse check is as follows: ![]() Both reports show that the required quantity of 247 pieces can be delivered in these parts:
As you see, the main lines of the report and the graphical browser are identical. However, where the ATP overview report stops at this point, the capable-to-promise overview shows which components or capacities were restrictive for delivering the entire quantity. This overview reads as follows:
You determine the dates as follows:
The available quantity is determined as follows:
Example Example: If 300 pieces of JOSUEF11 are required: ![]() The main lines for JOSUEF11 show 101 pieces available on December 20, and an additional 83 pieces on December 21. The component lines for JOSUEF14 show 101 pieces available on December 16 (lead-time offset applied) and 184 pieces on December 17. As a result, the available quantity of 184 is a cumulated quantity of 101 + 83 pieces. Although this method of showing the available quantity might be less transparent, this method shows extensive additional quantities for the components, rather than the cumulated quantities. From the main line, you can always see the amount of the additional quantity.
| |||