Initializing, Rolling and Updating ScenarioIn addition, you can use this session to:
If the Maintain Master Plans check box in the Items - Planning (cprpd1100m000) session is selected, you can also update a multisite scenario. LN also updates channel master plans. LN only updates the channel master plans that you specified in the Plan Item - Channels (cpdsp5100m000) session. Procedure This session carries out the following steps:
Note If a scenario is rolled forward, LN updates all plan items, regardless of what range of plan items is specified. Note If you specify a Scenario Finish Date for your scenario that does not match the end of the last plan period, the length of this last plan period is not equal to the plan period length you defined in the Scenario - Periods (cprpd4120m000) session. This leads to disproportionate planning values if you roll the scenario with the Initialize, Roll, and Update Scenario (cprpd4200m000) session.
| |||