| Printing Critical Material RequirementsLN prints a report about the critical material
requirements as displayed in the Critical Material Requirements (cprmp2505m000) session. To print a report of critical material
requirements: -
Select a range of: - Scenarios
- Plan periods, in
which the planned supply of the end items falls.
- Plan items (end
items)
- Periods in which the
components are required.
- Required plan items (components)
- Click Print
- Select a report type in
the Select Report list box and click OK.
You can select the following two types of
reports: Critical Material Requirements by Plan Item LN prints a report that lists all the critical
material requirements that originate from a specific plan item. Critical Material Requirements by Component LN prints a report that lists the items for
which a particular required item, or a range of required items, forms a
critical material requirement.
| |