| Copying Master Plan to ScenarioIn addition to copying
the various plan values, you can also modify these values by a certain
percentage. For example, you can use this to analyze what happens if the demand
is 10% higher and the inventory plan is 20% lower. Note LN only takes those items into account for
which the Maintain Master Plans check box in the Items - Planning (cprpd1100m000) session is selected. To copy plan data between scenarios: - A master plan must
already exist in the target scenario for each plan item and plan period
involved. You can check this in the Item Master Plan (cprmp2101m000) session. If the master plans do not exist yet, you
must first create them in the Initialize, Roll, and Update Scenario (cprpd4200m000) session.
- Specify the source
scenario.
- Specify the plan level
of the items for which the plan data must be copied. You can only copy data for
one plan level at a time.
- You can specify a
planner (optional). If you do so, LN only considers items that belong to this
planner.
- Select a range of plan
items.
- You can specify a range
of channels (optional). If you do not specify such a range, LN will not copy (demand
plan) data for channels.
- Select a range of plan
periods for which you want to copy plan data.
- Enter a percentage for
each type of plan that you want to copy.
- Specify the target
scenario.
- Select the update mode
( Overwrite or Add To.
- Optionally, select the Pro Rate check box.
- Click Copy.
Note The source scenario
and the target scenario do not need to have identical plan period definitions.
If necessary, LN redistributes the source plan period quantities over the target plan periods. | |