Creating or modifying a process to generate milestones
        
         
          - Open Infor Process Designer, and create a new or load an existing process file.
 
          - On the Info tab of process properties, select Generate Milestones.
 
          - Add or update activity nodes as needed.
 
          - On the Milestone tab of the activity property, specify this information:
           
            
             - 
              Is a milestone
             
 
             - 
              Select Is a milestone if the activity is a milestone.
             
 
            
            
             - 
              Label
             
 
             - 
              To customize a label, specify a label in the Label field. See Configuring milestone labels dynamically in User Action nodes for details.
             
 
            
            
             - 
              Run Mode
             
 
             - 
              Select a run mode.
              
               - 
                Pre-run only
               
 
               - 
                The pre-run phase is the act of executing a work unit to gather data to generate the Process Indicator model. During pre-run, only activity nodes marked as pre-run are executed. The pre-run execution phase happens before the runtime phase. Typically, pre-run is used for Landmark nodes that have record query definitions.
               
 
               - 
                Run time only
               
 
               - 
                The runtime phase is the actual work unit execution.
               
 
               - 
                Both (Run time + Pre-run)
               
 
               - 
                These nodes are executed during the pre-run and runtime phases. Typically, these are used by Landmark nodes that have CRUD (Create, Update, Delete) actions that also affect the pre-run phase.
               
 
              
              
            
             
          - Click Save.