Deploying pending cube configurations

Use this procedure to deploy pending cube configurations. Cube-based reporting allows for multi-dimensional reporting. Cubes are built-in tools for visualizing and sorting data.

  1. Select Administration Console > Configuration and Personalization > Configuration > Deploy Pending Cube Configurations or Configuration Console > Utilities > Configuration > Deploy Pending Cube Configurations.
  2. Specify this information:
    Scheduled Action Name
    Specify a name for the scheduled action. For example, ApplyPendingChanges.
    Notification Type
    Select a notification type for email and requests supporting user notifications.
    Email Address (Optional)
    Optionally, specify an email address.
    Email Address
    Specify an email address to receive a duration notification email if the deployment of the cube exceeds the threshold.
    Threshold Minutes
    Specify the number of minutes before sending the duration notification email.
    Schedule Type
    Select a schedule type. Some of the other fields in the window are based on this selection.
    First Time To Run
    Select a date and time and click Apply.
    Latest Time To Run
    Select a date and time and click Apply.
    Schedule Exclusion
    Select a schedule exclusion and click OK. If you select a schedule exclusion, you cannot select a schedule exclusion set.
    Schedule Exclusion Set
    Select a schedule exclusion set and click OK. If you select a schedule exclusion set, you cannot select a schedule exclusion.
    Run Action Concurrently
    Select an option to run the action concurrently. The default is No Request Concurrency.
    Strategy
    Select a strategy for an action failure configuration. The default is Run Once.
    Report Options
    Select a report option for an action failure configuration. The default is No Report.
    Threshold Minutes
    Specify the number of minutes before executing the action for an action failure configuration.
    Number Of Retries
    Specify the number of times for the system to retry the action for an action failure configuration.
    Continue On Failure To Run
    Select this check box for the system to continue if there is a failure to run.
  3. Specify information in the fields that apply to the schedule type that you selected.