Setting up IPA queue mappings

Use this procedure to set up queue mappings for Infor Process Automation. These mappings will control which queue work unit dispatching is assigned to and will enable you to set the priority for the work unit dispatching based on actor, data area, and process (flow definition) values.

To set up IPA queue mappings

  1. In the Async Administrator, select Setup.
  2. On the Async Setup page, select the Queues tab and select the queue that you want to set up IPA queue mappings for. (If the queue mappings for the queue will include processes (flow definitions) as one of the criteria, this should be a queue in the application data area.)
  3. Open the queue record.
  4. In the Mapping & Triggers section on the Queue form, select the IPA Queue Mappings tab and then click Create.
  5. On the Pfi Async Queue Mapping form, define a mapping:
    Actor

    An actor to use to determine whether a work unit is assigned to this queue. Blank means any actor.

    Data Area

    A data area to use to determine whether a work unit is assigned to this queue. Blank means any data area.

    Process
    A process (flow definition) to use to determine whether a work unit is assigned to this queue. Blank means any process.
    Priority
    Select the processing priority for this mapping within the current queue.
  6. Save your changes.