Opening a period for work

After scheduling a process, you must open a period for work to allow your resources to work on their tasks.

Note: 

Once a period is opened, no changes other than ownership can be made to the tasks.

  1. Select Close Setup > Manage Process and click the View Schedule tab.
  2. Select the scheduled process period and click the Open button.
  3. Click Yes to confirm that you want to open the period for work.