Allocation Types and Calculations
This topic describes allocation types and calculations.
Percent Allocation
This calculation multiplies each PO or TO line's total material cost by the user-entered allocation percent.
PO line total material cost = 120
PO Header % = .05
PO line Landed cost = 6
PO line unit cost = 6 / PO line qty ordered
Amount Allocation
This calculation distributes the user-entered estimated amount for each landed cost category evenly across all PO or TO lines according to the Allocation Method selected.