Change PO Status Utility

Use this utility to change the status of a specified range of POs from Ordered to Complete or Complete to History. These POs can be specified by either the Starting/Ending PO fields or the Starting/Ending Date fields.

When you run this utility, the system updates the vendor item cross reference's last cost with the PO line/release item cost, regardless of whether the Include Tax in Cost check box is selected on the PO. The system also updates the vendor item year-to-date cost with the total cost and is based on the quantity received and PO Line / Release item cost, regardless of whether the Include Tax in Cost check box is selected. This item cost may contain cost with or without tax amounts.

Note:  The status of Planned line items will not be changed.

When changing the status from Ordered to Complete, the following must occur:

  • All line items must have been fully received and vouchered.
  • All line items must have a status of Filled.