Greater than or Equal
-
Specify the minimum number of days that a task can deviate from the planned date. You can specify a negative value to indicate that the task was completed ahead of schedule.
-
Less than or Equal
-
Specify the maximum number of days that a task can deviate from the planned date. You can specify a negative value to indicate that the task was completed ahead of schedule.
Note: The values you specify in the Greater than or Equal and Less than or Equal fields cannot overlap across status colors.