Running the Job

  1. Click Play to run the job manually.
    A Run Options dialog box is displayed to verify how the job must be run. The main point of interest in the options dialog box is the Log Level. It defaults to Basic, but there are several log levels to consider: Nothing, Error, Minimal, Basic, Detailed, Debug, Row Level.

    See Log Levels.

  2. Click Run to run the job.
    After the manual run of the job is complete, the Job Metrics tab shows the results of the job. The step metrics that are available at the transformation level are not visible on the Job Metrics tab for the job run.
  3. Click the Logging tab to show the log for the job run.
    This completes the creation and running of the first job.