Changing the Last processing date

You can change the Last processing date for each document of a connection point.

  1. Select Connect > Active Connection Points.
  2. Select the connection point and click Rewind incremental.
  3. Select the document(s).
  4. Specify the last processing date. These options are available:
    • Reset to original starting point. The Last processing date is reset to the Do not include data from before value specified in the connection point.
    • Set to a specific date and time. You can set any date and time after the Do not include data from before value specified in the connection point.