Ending employee assignments for a posting project

Use this procedure to update employee assignment records if a project with multiple assignments ends early. The end date on employee assignments are updated with the Assignment End Date that is selected in this process. If any pending labor redistributions for an employee extend past the new assignment end date, that employee is excluded from this action.

  1. Select Projects and open a posting project record.
  2. On the Assignments tab, select Actions > End All Assignments.
  3. Specify a Finance Enterprise Group.
  4. Specify this information:
    Assignment End Date
    Select the new end date to use to update the employee assignment records.

    The end date on employee assignment records are updated if the end date is later than this Assignment End Date.

    Labor Schedule
    Specify a labor schedule to update the assignments with that labor schedule.  If this field is blank, then all assignments are updated.
  5. Click Submit.