Creating percentage of completions
- Select .
- Select the Structure tab.
- Open a project structure and select the Hierarchy tab.
- Open a summary contract project with a revenue method of Percentage of Completion.
- Click Contract Information.
- On the Project Funding tab, select a funding source.
- Select the Revenue Milestones tab and click .
- Specify this information:
-
Project Milestone
-
Specify a name for the milestone.
-
Date
-
Specify the projected achievement date for the milestone.
-
Amount
-
Specify the amount that is billed when the milestone is achieved.
-
Percent Complete
-
Specify the percent complete at which the milestone is billed. The value cannot exceed 100%.
-
Status
-
Select the status of the milestone.
- Select To Process to specify that the milestone is complete and will be billed when the milestone date is reached.
- Select Hold if the milestone is manually controlled instead of date-driven. You are required to remove the milestone before invoicing when this status is used.
- Select Historical to track a milestone that occurred before data was migrated to Project Ledger. Project Contract and Project Funding Source totals invoiced and recognized balances are updated by historical milestones.
-
Override Project
-
Select the posting project to post for the milestone amount.
- Click Save.