Manually creating a new process
        
         
          - Select .
 
          - On the Manage Process tab, select . 
 
          - Specify this information:
           
            
             - 
              Process Name
             
 
             - 
              Specify a name for the process.
             
 
             - 
              Team
             
 
             - 
              Select the team that owns the process.
             
 
             - 
              Process Owner
             
 
             - 
              Select the person from the designated team to own the process.
             
 
             - 
              Company
             
 
             - 
              Select the default company that is used for the process.
             
 
             - 
              Default Calendar
             
 
             - 
              Select the default calendar for the process.
             
 
             - 
              Default Period Group
             
 
             - 
              Select the default period group for the process.
             
 
             - 
              Schedule Tasks For Work Days Only
             
 
             - 
              Select this check box to assign tasks only on work days according to the designated calendar.
             
 
             - 
              Priority
             
 
             - 
              Select the priority for the process: Low, Medium, or High.
             
 
             - 
              Risk
             
 
             - 
              Select the risk for the process: Low, Medium, or High.
             
 
            
             
          - Click OK.