Interfacing asset and project capitalization individually

  1. Open the project interface control record and click the Draft Interface Records tab.
  2. Select Actions > Project Asset Interface.
  3. Click Submit.

    The Project Interface Control record is updated and the asset that is created when the asset interface record is released and is displayed when the Project Capitalization Interface is run.

    The records in the Draft Interface Records tab are moved to the Asset Interface Records tab.

  4. To create asset interface records for selected draft interface records, follow these steps:
    1. Select Conversion And Interfaces > Project Asset Interface Control.
    2. Open the project interface control record and click the Draft Interface Records tab.
    3. Select a draft asset interface records and click the Project Asset Interface button.