Creating draft project asset interface records
- Select Assets > Interfaces > Capitalization > Project Asset Interface Control.
- Open the project interface control record and click the Uncapitalized Transactions tab.
- Select Actions > Draft Project Asset Interface.
- Specify this information:
- Date
- Select whether to use the posting date or the transaction date to select transactions.
- Date Range
- Select the date range for the project asset records.
- Include Repairs
- Select this check box to include repair records.
- Summary Code
- To summarize records, specify a summary code.
- Override Transaction Date
-
Specify the override transaction date for the draft interface records.
Note: This is only applicable when Project Capitalization Upgrade is run.
- Override Project
- You must specify the override project if you specified a summary code and if the Project type in project interface control is Summary. This value will override the Asset Project in an asset item.
- Account
- Specify the alphanumeric account group number.
- Entity
- Select the accounting entity.
- Unit
- Select the asset account unit group.
- DM1 to DM10
- Specify the Finance Dimensions in their corresponding fields.
- Click Submit.
- To create draft project interface records for selected transactions, follow these steps:
- Select Assets > Interfaces > Capitalization > Project Asset Interface Control.
- Open the project interface control record and click the Uncapitalized Transactions tab.
- Select a record and click Draft Project Interface.
- Specify this information:
- Summary Code
- Specify a summary code to summarize records.
- Override Transaction Date
-
Specify the override transaction date for the draft interface records.
Note: This is only applicable when Project Capitalization Upgrade is run.
- Override Project
- Specify the override project if you specified a summary code and the project type in Project Interface Control is Summary. This value overrides the Asset Project in an asset item.
- Click Submit.