Submitting revenue reversal for approval for contract revenue by contract
If the enterprise project structure is set
to approve revenue recognition, then an action to submit revenue reversal for approval
is displayed. This action changes the approval status to Submitted For Approval. The status of the record remains in a
Journalized status. After the record has been
submitted for approval, the approver can approve or reject the records. When approved,
the record approval status is changed to Revenue Reversal
Approved. When rejected, a Comments
window is displayed. The approver must specify an explanation for the rejection. This
explanation appears in the body of the email that is sent for the record. Rejecting a
record changes the approval status to Rejected.
If one record is rejected, the entire group is rejected. The record can be deleted or
corrected and then resubmitted for approval. After the records are approved, then the
action to journalize can be run. All records in the run group must be approved before
journalizing.