Populating group effort
You can run an action to populate effort percentages from the average actual percentages. The last record is adjusted by the action for any rounding issues to a tenth of a percent when the average actual is not exactly 100.00%. When the Populate Effort Percent action is run, the percentages are overridden if they were manually specified. The Populate Effort Percent action can be run only when the system date is after the effort period end date. All labor periods must be processed for the effort period.