Copying budget allocation lines

Use this procedure to create an allocation line from an existing allocation line or create a copy of an existing allocation line. You can copy allocation lines between allocations that exist in the same allocation control or in a different allocation control with the same budget basis and budget dimensions. Data from the copied allocation line are default values for the new allocation line.

  1. Select Processing > Allocations > Allocation Control.
  2. On the Budgets tab, open an allocation control record.
  3. On the Allocation Lines tab, select the allocation line to copy.
  4. Click the Copy Allocation Line button.
  5. Specify the New Allocation Line and the New Description.
  6. Click Submit.