Revenue milestone splits can be copied to an existing milestone that has not been processed.
- Select Financials > Project Ledger > Setup > Project Setup.
- Select the Structure tab.
- Open a project structure and select the Hierarchy tab.
- Open a summary contract project and click Contract Information.
- Select the Project Funding tab and select a funding source.
- Select the Revenue Milestones tab.
- Select the milestone to copy and select Actions > Copy Revenue Distributions.
- Specify this information:
- To Milestone
- Select a revenue milestone to which to copy the split. Only milestones that do not have the status of Processed are displayed.
- Copy To All
- Select this check box to use the same revenue milestone split on all unprocessed records. If there is no split on a record, then a split is created.
- Replace Existing
- Select this check box to use the same revenue milestone split on all unprocessed records where splits already exist.
- Click Submit.