Scheduling production online
- Select Lists > Warehouse Schedule Planning Report.
-
Specify this information:
- Company
- Select a company.
- Location
- Select a valid stock location. It is also the production facility where finished goods are produced for work orders.
- Item
- Select the finished good for which you want to schedule production.
- Period End Dates
- These date fields are used to establish flexible time
fences to group demand records together. Each period date indicates the end of that
period.
Select a date in the Period 1 field to show the unscheduled demand after the date in the Previous field and up to the date in this field. The date that is selected in the Period 2 field shows unscheduled demand from the dates following Period 1 to the end date in Period 2.
- Date Used
- Select whether to show demand based on the Date Needed or the Production Start Date. If you select Production Start Date, the production lead time is factored in for that finished good as defined in Inventory Control.
- Document Demand View
- Select how to display the document demand during the
scheduling process.
Select Summary to display summary lines by period for orders and for requisitions. This option also consolidates demand from multiple demand sources onto one work order.
Select Detail to list orders and requisitions separately. Forecast demand is always summarized. This option also separates demand onto individual work orders.
- Select the group to receive the report.
- Click OK.