Project budget recommendations

We recommend that you use this information for project budgets.

  1. Create a single budget scenario for all project LTD budgets.
  2. Use imported budget data to create the project original budget.
  3. When the budget is in a ready state, use the incremental load action to add new projects budgets to the project budget scenario. Use incremental load to update the original budget amount.
  4. Use budget change requests to change or revise the original project budget. Using change requests for budget revisions maintains the integrity of the original budget. You can then report against the original budget or total budget including change requests. You can also view change history for each budget revision.