Changing date ranges

  1. Select Financials > Project Ledger > Setup > Project Setup.
  2. Click the Structure tab.
  3. Open a project structure and click the Hierarchy tab.
  4. Open a posting project and select Actions > Change Date Range.
  5. Specify this information:
    Begin, End
    The default value for the begin and end dates are the current dates from the project. Specify a new begin date, end date, or both.
    Update Summary Levels
    Select this check box to update the summary levels for the project for the specified date range.
  6. Click Submit.