Creating draft project asset interface records
-
Select .
-
Open the project interface control record and click the Uncapitalized Transactions tab.
-
Select .
- Specify this information:
- Select Transactions Through Date
- Select the through date for the project asset
records.
- Date
- Select whether to use the posting date or the transaction date to select
transactions.
- Include Repairs
- Select this check box to include repair
records.
- Summary Code
- To summarize records, specify a summary code.
- Override Project
- You must specify the override project if you specified a summary code and if the
Project type in project interface control is
Summary. This value will override the
Asset Project in an asset item.
-
Click Submit.