Unfinalizing allocations

Use this procedure to change the status of a finalized allocation run to Complete and make it unavailable for Birst analytics:
Note: You cannot unfinalize an allocation run that has been published for Birst reporting. You must first cancel the run and unpublish it for Birst reporting.

See Canceling allocations and Unpublishing allocations.

  1. Select TrueCost Allocation Controls and open an allocation control.
  2. On the Runs tab, select an allocation run with a status of Finalized, and then click Open.
  3. Select Unfinalize.