Configuring critical path settings

Critical path settings enable you to set the work week and work hours, which are necessary in defining the schedule for milestones and follow-up of styles. Defining the work days and work hours enables you to compare the working capacity of a user in a given time frame against the demands and deadlines of a particular activity.

  1. From the menu, select Setup > Settings.
  2. Click the Critical Path Settings icon.
  3. Specify this information:
    Work Day
    Select the corresponding check box to define a week day as a working day.
    Capacity
    Specify a number to define working hours in a day.
    Start Time
    Specify a number to define the start time in each work day.
  4. Specify non-working days.
  5. Specify the unit of measurement for tasks:
    1. Lead Time
    2. Work Load
    3. Buffer
  6. Click Save.

    The Calculated Averages fields are automatically updated based on the selected Work Day.