Configuring critical path settings

Critical path settings enable you to set your work week and work hours, which are necessary in defining the schedule for milestones and follow-up of styles. Defining the work days and work hours enables you to compare the working capacity of a user in a given time frame against the demands and deadlines of a particular activity.

  1. Select Admin > Configure - Infor Fashion PLM.
  2. Click Critical Path.
  3. To define the basis for calculating progress of your workload, select Number of activities or Workload.
  4. To define your work week, specify this information:
    Work Day
    Select the corresponding check box to define a week day as a working day.
    Capacity
    Specify a number to define working hours in a day.
    Start Time
    Specify a number to define the start time in each work day.
  5. To define nonworking days, specify this information:
    Date From
    Select a start date from the date picker.
    Date To
    Select an end date from the date picker.
  6. Click Save.