Enter Work Center for Rough-cut Resource Requirements

This procedure is used to enter the work centers used to calculate RCCP resource requirements. The RCCP calculation uses only work centers set as resource type 4 or 5.

Follow these steps

  1. Select 'Work Center. Open' (PDS010).

  2. Enter the name of the new work center.

  3. Enter either 4 or 5 in the Resource type field. For the latter, capacity must also be entered.

  4. Enter the necessary information in the other panels.

  5. For resource type 4 work centers, the ID must be entered in the Included in work center field for all work centers included.

  6. Specify option 12 to call 'Work Center. Change Capacity' (PDS015). Remember to re-create capacity by specifying option 22=Re-create.