Updating Work Request Status

This document explains how you update the status of a work request to indicate where it is in the planning process.

This process is usually performed by a maintenance planner or supervisor who decides whether a work request can be carried out with the resources that are available.

Outcome

The work request or operation receives a new status. The status indicates whether it is possible to proceed with the work (i.e. whether the work request or operation should be released to become a work order, or whether it needs to be replanned).

Information about the work request status is stored in these files:

Before you start

The work request must exist in 'Work Request. Open' (MOS170).

Description

Use one of these options to update the status of a work request to indicate where it is in the planning process.