Note: This action is not available for activity checklist components. It is available on other checklist components only if they are defined to require acknowledgment.
Select Development Planning > Checklists > Monitoring.
On the Resource Checklists tab, open the resource checklist to which the checklist component belongs.
On the Components tab, select the acknowledged checklist component and select Actions > Revert Acknowledgment.
On the pop-up dialog, specify this information:
Reason
Required. Select the reason code. The reason code must be defined with a subject of HCMEmployeeRevertChecklistActions.
Comment
If applicable, specify additional information.
Click OK.
If the previous status was Awaiting Validation, the new status is Awaiting Acknowledgment And Validation.
If the previous status was Complete, the new status is Awaiting Acknowledgment And Validation, or Awaiting Acknowledgment (depending on whether the checklist component was defined to require validation).