Using the model rate progression with steps in step and grade schedules

You can run the Model Rate Progression With Steps action in a step and grade schedule that includes rate progression rules.

  1. Select Administration > Setup.
  2. On the Step And Schedules pane, select Step And Grade Schedules.
  3. Select a step and grade schedule with rate progression rules.
  4. Click More Actions, then select Model Rate Progression With Steps.

    If you run the action, you can select the step and grade record, and then open the Proposed Step Rate Increase tab to view the changes.

  5. Specify this information:
    Increment By
    Select percent or amount, then provide the percentage or amount.
    Process As Of Date
    Specify the effective date.
    Reason
    Select the reason.
  6. Click Submit.

    The Proposed Step Rate Increase and Modeling tabs are displayed.

    Note: This action is only available for schedules with rate progression rules.