Note: This status occurs only if you cancel a resource checklist
and then reactivate it without selecting the option to reactivate checklist
components.
Select Development Planning > Checklists > Monitoring.
On the Resource Checklists tab,
open the resource checklist to which the checklist component belongs.
On the Components tab, select
the waived checklist component and select Actions > Revert Cancellation.
On the pop-up dialog, specify this information:
Reason
Required. Select the reason code. The reason code must be defined
with a subject of HCMEmployeeRevertChecklistActions.
Comment
If applicable, specify additional information.
Click OK.
Non-activity checklist components revert to their status before they
were cancelled. Cancelled activity checklist components revert to Needs registration.