Calculating future projected balances

You can calculate a resource's future projected balance for a specific date.

  1. Select Absence Management > Absence Analysis > Resource Plans.
  2. Open a plan and select the Future Projected Balances tab.
  3. Click Calculate Balance.
  4. Specify this information:
    Date
    Select the date for which to calculate the projected amount of hours and days that will be earned by this resource.
  5. Click Submit.
    The projected amounts of hours and days are displayed for the specified date.