Building report cubes

  1. Select Administrator > Utilities > Refresh Cubes.
  2. Click Create.
  3. Specify the cube name as EmployeeTimerecord.
  4. To add more detail to the log file, select Verbose.
  5. To stop the cube from processing, even if there is a scheduled action set to reload or refresh the cube, select Pause.
  6. Click Save.
  7. To immediately rebuild the entire cube, select Actions > Reload.
  8. To immediately update the cube with any changes to the dimensions and fact rows that have taken place since the last Refresh or Reload date, Actions > Refresh.