Reverting waived checklist components

  1. Select Learning and Development > Checklists > Monitoring.
  2. On the Resource Checklists tab, open the resource checklist to which the checklist component belongs.
  3. On the Components tab, select the waived checklist component and select Actions > Revert Waive.
  4. On the pop-up dialog, specify this information.
    Reason

    Required. Select the reason code. The reason code must be defined with a subject of HCMEmployeeRevertChecklistActions.

    Comment

    If applicable, specify additional information.

  5. Click OK.

    Non-activity checklist components revert to their status before they were waived. Activity checklist components revert to Needs registration.