Completing or failing to complete resource activities

A resource or resource manager can report an activity as finished.

  • If a resource activity is associated with a session, then the activity is shown on the Finalize Activity Completions page as information to the learning manager. The learning manager can then complete the resource activity by completing the resource's session participation. Alternatively, the learning manager can fail to complete the resource activity.
  • If a resource activity is not associated with a session, then the activity is shown on theFinalize Activity Completions page. The learning manager can then complete the resource activity. If the activity is not required, then the learning manager can fail to complete the resource activity.
  1. Select Registration And Completion > Finalize Activity Completions.
  2. Select an activity.
  3. Click the ellipsis and select Finalize.
  4. Specify this information:
    Date Completed
    Specify the date that the activity is finalized. If the activity has an end date, then the field is populated with the end date from the class records. You can change the end date.
    Score
    Specify a score for the participant.
  5. Click Submit.