Mass terminate by resource

  1. Select Absence Management > Enrollment > Mass Terminate.
  2. Specify this information:
    Processing Option
    Select By Resource.
    Organization Unit Group
    Optionally, specify an organization unit group for which to process resource plans.

    All resources whose primary work assignment's Organization Unit is within this Organization Unit Group are processed.

    Resource Group
    Select a specific resource group.
    Resources
    Select to run for up to eight individual resources.
    Plan Type
    Specify a plan type from which to terminate resources.
    Eligibility Groups
    Select one or more eligibility groups. If this field is blank, all eligibility groups are processed.
    Resource Plan End Date
    Specify the plan end date to update on the selected resource plan records. Not required.
    Accrual End Date
    Specify an accrual end date. Resource plan records with one of these criteria are selected:
    • A blank accrual end date.
    • An accrual end date that is greater than the date that is specified.

    This date is set as the Accrual End Date on the selected records. Required.

    Set Override
    Select this check box to set the Override Plan Dates And Accrual End Date option on selected resource plan records. Selecting this check box prevents reactivating the resource plan record for future eligibility group updates when Recalculate Enrollments is run.
    Include Non-Zero Available Balances
    Select this check box to terminate records with available balances, including negative balances. If this field is not selected, then only resource plan records with no available balances are included.
    Update
    Specify an update option.
    • List Plans To Terminate: creates a list of records to terminate.
    • Terminate Plans: Terminates the plans that match the selection criteria. It is important to use the same selection criteria to terminate as you did when you generated the List Plans To Terminate.

      See Update fields in set actions

  3. Click OK to process this action immediately or click Schedule to schedule the action to run later.