Stopping job operations for a team

Use this form to stop job operations for a team. You can use this transaction to report completed and moved quantities, scrap items, and assign lot and serial numbers when stopping job operations. To access the End Team Run form, you must be assigned to the Administrator, TeamLeader,or Supervisor permission group. To stop job operations for individual employees, see Stopping Job Operations.
Note: The End Run Common form is displayed that allows you to stop the job operations for a single employee or team or workset, when you enable the feature (RS8558) check box on the Feature Management form. See Stopping job operations for a single employee, team or workset.

To stop a job operation:

  1. Select Labor > End Team Run. The End Team Run form is displayed.
    Note: If the End Team Run form is started from the Home page, the form defaults the job fields for the employee. If no start record is found, the form displays the message: Employee: xxx does not have a run transaction running with an OK option. When the employee clicks the option, the form is closed.
  2. Specify a date and time to record for this transaction. The current date and time are specified by default. You can only modify the date and time if the employee user ID has the appropriate authorizations on the Users form.
  3. Specify the team name or team badge ID.
  4. Specify a job and job suffix. The item number, unit of measure, warehouse, and job status are displayed along with the total, scrapped, completed, and remaining quantities.
  5. Select the Progress tab to view the current progress of each operation in the selected job.
  6. Select the operation number you are stopping. The work center where the operation is performed is displayed along with the time the operation started and the elapsed time.
  7. Specify or review this information:
    Good
    The number of completed items for the selected operation.
    Moved
    The number of completed items to move to the next operation.
    Note:  The value is specified by default. This field is unavailable if the Time Track functionality is implemented and this is the last operation on the order.
    Complete Operation
    If you are completing the operation, select this check box.
    Note: This check box is available only if Allow Operation Complete is selected for this transaction.
    Close Job
    If you are completing the operation and it is the last operation on the job, select this check box.
    Note: This check box is only available if Allow Close Job is selected for this transaction.
    Combine Labor and Machine Time
    Select this check box to report machine time as a ratio of labor time for this operation. Clear this check box to report machine time manually in a separate transaction.
    Note: This check box is available only if the Combine Labor and Machine Time check box is selected for the team on the Team Maintenance form and the Time Track functionality is implemented.
    Machine Ratio
    The machine ratio. The machine ratio determines the portion of the reported labor time is reported for the machine. For example, a ratio of .5 will report half the reported labor time for the machine.
    Note: This field is only displayed only if Combine Labor and Machine Time is selected and the Time Track functionality is implemented. However, this field is unavailable and machine time is reported as a one-to-one ratio to labor time, if Combine Labor and Machine Time check box is selected and Time Track functionality is not implemented.
    Resource ID
    The resource ID of the employee.
    Note: 
    • Employees can select a resource ID for starting a labour transaction only if the- Combine Labor and Machine Time check box is selected.
    • You can view the Resource ID field on start and end forms, only if the Display Resource ID is selected.
    • The resource ID displays resources that are in the resource groups on the Syteline job operation's forms resource tab.
    • Employee can select resources associated with the job, only if the Only allow job resource parameter is selected. However, employee can enter any valid resource if Only allow job resource is not selected.
    • The Machine Resource field is displayed and the value is based on the validation of the resource ID field.
    • When a Team run is completed, the resource ID is included on the record for the first member of the team who started the run.
    • The resource ID follows the same logic as that of recording the quantity.
    Location
    If applicable, specify the stock location where the completed items are to be received. This field is only available if the last operation of the job is selected and if the Put Away parameter is selected for this transaction.
    • If applicable, use the Details tab to display operation related data. The tab displays the received quantity of the operation.
    • If applicable, use the Scrap tab to scrap items. See Scrapping Items for details. This tab is only available if Allow Scrap is selected for this transaction.
    • If applicable, specify the lot number on the Lot/Serial tab.
    • If applicable, select the arrow button on the Lot/Serial tab to assign serial numbers. See Assigning Serial Numbers for details. You must assign all unassigned serial numbers to stop the operation.
    • To stop the selected operation, select the green process button.
    If you are creating a new lot, you might be prompted to specify lot attributes. If the Lot Attributes form is displayed, specify lot attributes. See Specifying Lot Attributes for details.

    Backflush Lots and Serials functionality is added. Also, an update is added to the posting logic to record all the quantities to the employee who performs the transaction instead of splitting across the team members. This logic is stable to deal with regular as well as serial controlled items and the update backflush data accordingly.