Stopping job operations

Use the this form to stop job operations.

Note: The End Run Common form is displayed which allows you to stop the job operations for a single employee or team or workset, when you enable the feature (RS8558) check box on the Feature Management form. See Stopping job operations for a single employee, team or workset.

To stop a job operation:

  1. Select Labor > End Run. The End Run form is displayed..
  2. Specify a date and time for the record.
    Note: The current date and time is specified by default. You can modify the date and time only if the employee is authorized on the User Extensions form.
  3. Specify a job and job suffix.
    Note: The item number, unit of measure, warehouse, and job status are displayed along with the total, scrapped, completed, and remaining quantities. 
  4. Select the Progress tab, to view the current progress of each operation in the selected job
  5. Select the operation number to be stopped. The work center to perform the operation is displayed along with the time the operation started and the elapsed time.
  6. Specify or review this information:
    Good
    The number of completed items for the selected operation.
    Moved
    The number of completed items to move to the next operation.
    Note: This value is specified by default. If Time Track is not implemented and this is not the last operation on the order, this field is unavailable.
    Complete Operation
    Select this check box, if you are completing the operation, . 
    Note: This check box is available only if Allow Operation Complete is selected for this transaction.
    Close Job
    Select this check box, if you are completing the operation and it is the last operation on the job, . 
    Note: This check box is available only if Time Track is not implemented and Allow Close Job is selected for this transaction.
    Combine Labor and Machine Time
    Select this check box to report machine time as a ratio of labor time for this operation. Clear this check box to report machine time manually in a separate transaction.
    Note: This check box is available only if the Combine Labor and Machine Time check box is selected for your employee type on the Employee Types form and Time Track functionality in Infor Factory Track is implemented.
    Machine Ratio
    The machine ratio. This ratio determines what portion of the reported labor time is reported for the machine.
    Note: For example, a ratio of .5 reports half the reported labor time for the machine. This field is only displayed if Combine Labor and Machine Time is selected and if the Time Track functionality in Infor Factory Track is implemented. Specify a machine ratio. If the Time Track functionality is not implemented and the Combine Labor and Machine Time check box is selected, this field is unavailable and machine time is reported as a one-to-one ratio to labor time.
    Resource ID
    Employees can select a Resource ID for starting a labour transaction if the Combine Labor and Machine Time check box is selected.
    • You can view the Resource ID field on start and end forms, only if the Display Resource ID is selected.
    • The Resource ID displays resources that are specified in the resource groups, in the Resource tab on the Syteline job operations form.
    • Employee can only select resources associated with the job, if the parameter Only allow job resource is selected. However, employee can enter a valid resource only if Only allow job resource is cleared.
    • The Machine Resource field is displayed and the value is based on the validation of the resource ID field.
    Location
    The stock location where the completed items are to be received. This field is available only if:
    • the last operation of the job is selected
    • the Put Away parameter is selected for this transaction
    • and Time Track is not implemented
    Issue to Parent
    Select Yes to issue completed items from this sub-assembly job to its parent job. This field is displayed only if:
    • the Prompt for issue to Parent Job parameter is selected on the Generic MES_JobMove Parameters form
    • a parent job is defined as the destination for the completed items
    • this is last operation for this sub-assembly job
    To Container
    Select this check box to issue the completed items to a container. 
    Note: This check box is displayed only if this is the last operation when the Time Track functionality is not implemented.
    Container
    The container to which you must issue the completed items. To generate a new container number this field must not be specified.
    Note: This field is displayed only if the To Container check box is selected.
    • Use the Details tab to display operation related data. The tab displays the received quantity of the operation.
    • Use the Scrap tab to scrap items. See Scrapping Items for details. This tab is available only if Allow Scrap is selected for this transaction.
  7. Click Process.