Starting labor hours reporting for a service order

  1. Select Material > Start Project Labor. The Start Project Labor form is displayed.
  2. Specify the date and time to record for this transaction, if required.
    Note: The current date and time is specified by default. You can modify the date and time only if the employee is authorized on the User Extensions form.
  3. Specify this information:
    Project
    The project number. The project name, customer, start date, and project type are displayed on the Details tab.
    Task
    The task.
    Cost Code
    The cost code.
  4. Click Process, to start reporting labor hours for the project.
  5. Click Close,to close the form without reporting labor hours.