Reporting completed and moved quantities using the work center form

You can report completed and moved quantities for operations that are running.

  1. Select Labor > Work Center. The Work Center form is displayed.
  2. Specify the employee ID in the field marked with a person icon.
    Note: This number is specified by default.
  3. Select a work center, in the field marked with a factory icon.
    Note: The work center is specified by default.
  4. Select the Active Transactions tab, to view the operations on which you are currently working.
  5. Select an operation.
  6. Select Job Move. The Job Move form is opened. Use this form to report completed and moved tasks.